A job describes what must be done, on which equipment and how often. This page explains how to create a job and schedule it.
Job types
- Planned jobs repeat by interval.
- Condition based jobs are created when a measured value crosses a limit.
- Unplanned jobs are one-off repairs reported by the crew.
Create a job
- Open PMS > Jobs and select New job.
- Choose the vessel and the equipment.
- Enter a clear job title and a short description of the work.
- Select the responsible rank, for example Chief Engineer.
- Set the interval and save the job.
Intervals
The interval decides when the next work order is created.
| Interval type | Example | Next due date is calculated from |
|---|---|---|
| Calendar | Every 3 months | Last completion date |
| Running hours | Every 2,000 hours | Counter value at last completion |
| Whichever first | 3 months or 2,000 hours | The one that is reached first |
Grace period
Add a grace period to keep a job from being shown as overdue for a few days after its due date.
Link spare parts
Link the spare parts a job consumes. When the job is completed, the used quantity is deducted from the vessel stock automatically.
Tip: Link only the parts you always need. Optional parts can be added while completing the work order.
Best practices
- Keep job titles short and start with a verb, such as "Inspect fuel pump".
- Use job descriptions for safety precautions and required tools.
- Review overdue jobs weekly.